4
Projects Approved
₹ 9,82,93,219.67 Cr.
Total Cost of Approved Projects
₹ 4,01,08,856.00 Cr.
Amount Released to City
48.31%
Physical Completion

Progress till January 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Integrated development and improvement of arterial road transportation infrastructure, parking and signage work at Badami. 6,46,30,801.00 2,75,37,050.00 Jul, 2017 Mar, 2019 55.00 Rs. 68214900.00 is approved cost of Entrance arches and Junction Improvement. CPWD has awarded tenders, contractor will start the works very soon
2 Zero Waste Management at Badami town 85,02,142.00 46,00,000.00 Aug, 2017 Jan, 2019 92.00 Civil works completed 100 % , electrical works completed, Bio gas unit work under progress, e rikshaw, Mechanical eqipments work order issued . Final tender cost(in lakhs): civil=85.02, Electrical=21.00, Bio gas unit= 37.50, Mechanical instruments = 8.38, e -rikshaw =6.25, Total=158.15
3 Under Ground Drainage work at Tatakoti Badami 42,40,017.67 37,87,755.00 Apr, 2017 Jan, 2019 97.00 Due to ASI prohibitted area, working manually.
4 Improvement of Historic Vernacular Building Facade and streetscape at Badami. 2,09,20,259.00 41,84,051.00 Oct, 2018 Mar, 2019 0.00 CPWD has Awarded tenders, Contractor started the work.
  Total 9,82,93,219.67 4,01,08,856.00