8
Projects Approved
₹ 18,55,17,724.00 Cr.
Total Cost of Approved Projects
₹ 36,64,97,231.00 Cr.
Amount Released to City
38.75%
Physical Completion

Progress till February 2019

Sr. No. Name of Project Final Project Cost (₹ Cr.) Amount released to City (₹ Cr.) Actual Start Expected finish % of physical completion Remarks
1 Redevelopment and Revitalisation of Vrindavan Parikrama Marg 6,08,20,000.00 7,68,38,648.00 Jan, 2017 Mar, 2019 76.00 Original tendred cost was Rs. 71412606.00, works of Rs. 60820000.00 are in progress. Percentage of physical completion of the project is revised as per updated tendered cost.
2 Revitalization of Historic Krishna Janmbhoomi Precinct 3,71,97,724.00 5,20,97,724.00 Jan, 2017 Mar, 2019 69.00 Original tendred cost was Rs. 126814269.00, works of Rs. 37197724.00 are in progress. Percentage of physical completion of the project is revised as per updated tendered cost.
3 Rejuvenation of Historic Vishram Ghat 3,25,00,000.00 0.00 Jun, 2018 Jan, 2019 0.00 None
4 Revitalization of the Historic Chatta Bazaar 5,50,00,000.00 3,91,12,038.00 May, 2018 Mar, 2019 0.00 Final Tender Cost is of package 1.
5 Proposal for Installation of CCTV Cameras at Krishna Janmastan, Vrindavan Parikarma Marg & Vishram Ghat 0.00 0.00 Feb, 2019 Mar, 2019 0.00 Work to be awarded.
6 Proposal for Beautification of Krishnapuri Tiraha at Mathura 0.00 0.00 Feb, 2019 Mar, 2019 0.00 -
7 Facade Lighting at Potra Kund at Mathura 0.00 19,84,48,821.00 Feb, 2019 Mar, 2019 0.00 -
8 Installation of Street Furniture etc 0.00 0.00 Feb, 2019 Mar, 2019 0.00 Work to be awarded.
  Total 18,55,17,724.00 36,64,97,231.00